PROJECT SCHEDULE:
Bid Date: Summer 2015
Construction Start Date: Fall 2015
Anticipated Bridge Closure: May 2016-July 2017
Estimated Completion Date: Summer 2017

 

 Reconstruction of Bridge MA-14 County Route 6
(Amboy Avenue/West Front Street) over the Matawan Creek  Presentation

PROJECT SUMMARY SHEET
Reconstruction of Bridge MA-14 on County Route 6, Amboy Avenue/
West Front Street, over Matawan Creek in the Township of Aberdeen