10/23/2019 - CONSTRUCTION UPDATES

*** CONSTRUCTION UPDATE***


The Borough has two contractors working on road jobs at various locations around town. The updated work schedule is listed below:

Esposito Construction

Week of 10/21:
- Concrete: Finish Kearney Street and begin Hurley Street
- Paving: Mill/Pave Kearney Street

Week of 10/28:
- Concrete: Finish Hurley Street
- Paving: Mill/Pave Hurley Street

Week of 11/4:
- Concrete: Start Warren Street
- Storm Sewer: Two days of pipe work on Main Street

Week of 11/11:
- Concrete: Finish Warren Street and start Main Street
- Paving: Mill/Pave Warren Street

Week of 11/18:
- Concrete: Continue concrete on Main Street

Week of 11/28:
- Concrete: Finish concrete on Main Street
- Paving: Begin Milling/Paving Main Street

Week of 12/4:
- Concrete: Start/Finish concrete on Butler Street
- Paving: Finish Milling/Paving Main Street

Underground Utilities Corporation - UCC

Week of 10/20
Cement work on:
- Fulton St & 3rd St
- Green Grove Ave & 3rd St
- 3rd St
- W. 3rd St & Broad St

Week of 10/27
Cement work on:
- Kearney Street from Pershing Pl. To Henry Hudson Trail

Week of 10/3
Cement work on:
- E. Front St between Osborn & Church

Timing TBD depending on Test Pit Results
- Install Division St Drainage
- Install E Front St Drainage
- Sanitary Sewer E Front & Division Sts

Please observe the posted parking restriction in these areas and be mindful of the traffic directors on duty while construction is taking place. Please put you trash out as scheduled. If it is not picked up, please do not take it in. Call the borough and we will have it picked up 732.739.5122.

On behalf of the Mayor and Borough Council, thank you for your patience as we work to make these important improvements.

Should you have any questions or comments on this project, please contact Borough Administrator Steve Gallo at 732.739.5122 or via email at sgallo@keyportonline.com